Guide

Pool Removal Approval Fees NSW: DA, CDC and Certifier Costs Explained

Hunter Pool Removals is an independent referral service and does not perform or contract for the advertised work. Your enquiry may be referred to an independent contractor. Where licensing is required, the contractor's identity and licence details will be provided before you accept a quotation or enter a contract.

Pool removal approval fees in NSW depend on the pathway and the council. There is no single NSW DA fee: each Hunter council publishes its own 2026/27 schedule, none has a separate line for pool demolition, and a DA falls into the building or works bands by estimated cost. For works up to $5,000 the DA fee is $153 at City of Newcastle and Maitland, $152 at Lake Macquarie and Port Stephens, and $147 in Cessnock’s schedule for adoption. Council CDC fees run from City of Newcastle’s fixed $750 pool demolition line to Lake Macquarie’s “market price”, and private certifiers set their own prices. Exempt development, where it applies, needs no application, but it covers far less than many pages claim.

All figures below are from each council’s own 2026/27 fees and charges, linked in the tables. The council approval guide explains the pathways in full.

Quick answer

  • Exempt: no application and no fee, but only for a narrow class of minor structures (below).
  • CDC (complying development certificate): the usual route for removing a whole pool. Council fee $413 at Port Stephens (its single dwelling demolition line) or $750 at City of Newcastle (its pool demolition line); other councils price it differently, and private certifiers set their own fee.
  • DA (development application): needed where a CDC is not available, such as many heritage sites and, on Kiama Council’s reading of the state rule, a partial fill-in. Council lodgement fee for works up to $5,000 is $153 at City of Newcastle, more for larger estimates, plus any reports the application needs; each council’s figure is in the table below.

When is pool removal exempt development?

NSW Planning says demolition can be exempt development only if it relates to a minor building or structure that could itself be built or installed as exempt development, and the work must follow AS 2601-2001 (NSW Planning, Demolition of buildings, updated 23 March 2026). Whether a particular pool counts is a question for a certifier or the council. For a typical in-ground pool, plan on a CDC or a DA.

When is a CDC (Complying Development Certificate) required?

NSW Planning says demolition of a dwelling and detached development “including garages and swimming pools” can usually be done under a CDC issued under the Demolition Code, provided pool piping is removed and the site is restored to the adjoining ground level with compacted fill. City of Newcastle’s demolition guide says a CDC needs a demolition plan, a statement of compliance with the Demolition Code and “Hunter Water stamped” plans, and is not available on heritage items or, with some exceptions, in heritage conservation areas (City of Newcastle, Demolition). The pool removal CDC guide covers the code’s conditions.

Council CDC fees, 2026/27:

CouncilCDC fee itemSource
City of Newcastle$750, “Swimming pools … demolition work” line, incl. GSTNewcastle Fees and Charges 2026/2027, p.75
Lake MacquarieCDC assessment: “Market price per application” (no fixed fee)Lake Macquarie fee table 2026/2027
MaitlandUp to $5,000: min $115 plus $3 per $1,000, max $150 plus $9 per $1,000; $5,001-$50,000: min $155 plus $2.50 per $1,000, max $230 plus $7.50 per $1,000Maitland Fees and Charges 2026/27, p.36
Cessnock (schedule for adoption)Residential or Class 10 CDC: “equivalent construction certificate fee plus 30%” (no demolition line)Cessnock Fees and Charges 2026-2027, p.44
Port Stephens$413, CDC demolition of a single dwelling line, incl. $37.55 GSTPort Stephens Fees and Charges 2026/27, p.77

Private accredited certifiers also issue CDCs at their own prices, so a council’s CDC fee is only the council’s price. No published source gives a typical private certifier fee for a pool removal; ask each certifier for a written fee that says which inspections it includes.

When is a DA (Development Application) required?

A DA is the route when the work does not fit exempt or complying development. The common Hunter triggers:

  • Heritage. City of Newcastle says a CDC is not available on heritage items or, with some exceptions, in heritage conservation areas. A 2024 state fact sheet says the Demolition Code now allows pools to be demolished in heritage conservation areas (DPHI fact sheet); the two word it differently, so a certifier can confirm. See heritage-listed property pool removal.
  • Partial fill-in. Kiama Council’s fact sheet on the state rule says partial removal “could not be done as Complying Development” and would need a DA (Kiama Council fact sheet, 1 September 2021). None of the five Hunter councils publishes an equivalent sheet, so ask a certifier.
  • Mine subsidence is not itself a DA trigger. Demolition is on Subsidence Advisory NSW’s exempt developments list; backfill is not listed either way, so ask Subsidence Advisory whether the fill, or anything built over it later, needs approval.

Council DA fees, 2026/27 (building or works, including demolition): the smallest band covers works estimated at up to $5,000 and the next runs to $50,000 (City of Newcastle schedule, p.62).

CouncilSmallest bandNext bandSource
City of Newcastle$153$235 plus $3 per $1,000 (or part) over $5,000Newcastle Fees and Charges 2026/2027, p.62
Lake Macquarie$152$234 plus $3 per $1,000 “of the estimated cost”Lake Macquarie fee table 2026/2027
Maitland$153$235 plus $3 per $1,000 “of the estimated cost”Maitland Fees and Charges 2026/27, p.27-28
Cessnock (schedule for adoption)$147$226 plus $3 per $1,000 over $5,000Cessnock Fees and Charges 2026-2027, p.29
Port Stephens$152$234 plus $3 per $1,000 over $5,000Port Stephens Fees and Charges 2026/27, p.67

The fee is set by the estimated cost of the works. As a simple sum on City of Newcastle’s schedule, works estimated at $12,000 give a DA fee of $235 plus 7 x $3, which is $256. The pool removal cost guide has the published price ranges that drive the estimate.

A DA may also need supporting reports, such as a statement of environmental effects and a waste management plan, which City of Newcastle lists for a demolition DA. No published source gives a Hunter price for a heritage impact statement or similar report; ask the consultant for a written fee.

Other council fees that can apply

CouncilItemFeeSource
City of NewcastlePre-DA, minor proposals$375, GST YNewcastle Fees and Charges 2026/2027
City of NewcastleHeritage notification, works to single dwelling$94, GST NNewcastle Fees and Charges 2026/2027
MaitlandHeritage Minor Works Approval$110, incl. $10 GSTMaitland Fees and Charges 2026/27, p.41
Cessnock (schedule for adoption)Minor Heritage Works advice$197.26, GST YCessnock Fees and Charges 2026-2027
Port StephensPre-lodgement meeting, minor development$720, incl. GSTPort Stephens Fees and Charges 2026/27, p.57
Port StephensDewatering permit (covers emptying a pool to stormwater)$1,020 per applicationPort Stephens Fees and Charges 2026/27, p.93

A section 68 approval under the Local Government Act is separate from the DA or CDC and only applies where the job touches one of its listed activities; in the Hunter the plumbing side mostly runs through Building Commission NSW and Hunter Water instead, as the section 68 guide explains. If the council says one applies, ask it for the fee in writing.

Once the pool is gone, ask the council to update the NSW Swimming Pool Register; several councils list a small registration fee, for example $10 at Maitland (p.53) and Port Stephens (p.84).

NSW Planning Portal search confirmation

Before you commit to a quote, find out what applies to your land. A section 10.7 planning certificate from council gives a property’s zoning, planning controls and constraints such as land contamination, flooding and bushfire prone land (NSW Planning Portal, Section 10.7 planning certificates, updated 14/12/2023). Heritage listing and mine subsidence district status are worth checking too; a certifier or the council can then confirm the pathway and the fee.

FAQs

Can my pool removal contractor determine if I need a DA or CDC?

A contractor can tell you what it usually sees, but only a council or an accredited certifier can confirm the pathway. Pre-lodgement advice is not free at every council: City of Newcastle lists $375 for minor proposals (fees) and Port Stephens $720 for a minor development meeting (fees, p.57) in 2026/27.

Is there one DA fee for pool removal across NSW?

No. The Hunter councils’ 2026/27 schedules differ: $153 at Newcastle and Maitland, $152 at Lake Macquarie and Port Stephens, and $147 in Cessnock’s schedule for adoption, for works up to $5,000. None has a pool demolition line; the DA fee table above links each council’s schedule.

Are heritage consultant fees negotiable?

No published source gives Hunter heritage consultant fees, so compare written quotes. Ask the council first what reports it will need, so you only pay for what the application requires.

Does the certifier fee include the inspection?

It depends on the certifier. The council CDC lines above do not spell out which inspections are included, so ask for a written fee that lists them.

Request a quote

Sources

Last reviewed 16/11/2026. How these pages are researched and corrected.

More guides

What Equipment Is Used to Remove a Pool?

The machines on a pool removal job: excavators, hydraulic breakers, loaders, tippers and compactors, how access…

View

Pool Removal in Wet Weather: What Rain Does to Scheduling and Cost

Can pool removal go ahead in rain? Which stages stop, why backfill is the weather-sensitive step, BOM rainfall for…

View

Pool Removal Before a Knock-Down Rebuild

Knock-down rebuild on a block with a pool: why full removal usually suits, how it fits the house demolition, the fill…

View

More on this topic

Request a quote

Tell us about the job and an independent local contractor can quote it.

Get a Quote