Section 68 of the Local Government Act 1993 is a list of activities that need approval from the local council, such as sewerage and stormwater drainage work, putting a waste container in a public place, or hoisting goods over a public road. It is not the approval for demolishing the pool itself: that is a planning approval, usually a complying development certificate (CDC) or a development application (DA). Section 68 only comes into a pool removal where the job touches one of the listed activities, and in the Hunter the plumbing side mostly runs through Building Commission NSW and Hunter Water instead. The planning side is covered in the pool removal council approval guide.
What is Section 68?
The NSW Planning Portal describes section 68 as specifying “a range of activities where approvals are required to be obtained from the local council” (NSW Planning Portal, Section 68 approvals, updated 02/12/2025). The groups that could touch a pool job are:
- Water supply, sewerage and stormwater work: including “carry out sewerage work”, “carry out stormwater drainage work” and “connect a private drain or sewer with a Council controlled public drain or sewer”.
- Management of waste: including “put a waste storage container in a public place” and “dispose of waste into a Council sewer”.
- Public roads: “swing or hoist goods across or over any part of a public road” by a lift, hoist or tackle over the footway.
The other groups (community land, caravan parks, amusement devices and so on) have nothing to do with a backyard pool.
How does this work in practice?
The demolition approval comes first, and it is not s68. NSW Planning says demolition of a dwelling and detached development “including garages and swimming pools” can usually be done under a CDC, and demolition is exempt only where the structure could itself be built as exempt development (NSW Planning, Demolition of buildings); Lake Macquarie City Council says demolition that does not meet those codes needs a DA (Lake Macquarie City Council, Demolition). Where demolition removes a pool, the Demolition Code also requires any piping to be removed and the site restored to the adjoining ground level with compacted fill.
Plumbing is regulated by the state in the Hunter. In the Newcastle and Hunter area, plumbing and drainage work that needs an inspection is notified to Building Commission NSW through the MyInspections Gateway before it starts, and the plumber completes a Certificate of Compliance when it is finished; outside the Sydney Water and Hunter Water networks, the local plumbing regulator handles this instead (NSW Government, Plumbing inspection documents). So capping a pool’s water and backwash lines is normally the licensed plumber’s paperwork, not a council s68 permit you lodge yourself. The plumbing and electrical decommissioning guide sets out who does what.
The s68 items that can still apply are the council-facing ones: work on a council stormwater drain or kerb outlet, a skip or bin left on the road or footpath, or a crane lifting a shell over the footway. Ask the contractor whether any of these is part of their method, and who arranges the approval.
When might s68 cause delays?
Draining the pool to the street. Pool water should not go to the gutter or stormwater without council approval. Port Stephens Council says “Council approval is required before any water can be discharged into Council’s stormwater drainage system, including road gutters”, through a Temporary Dewatering Permit that needs a dewatering management plan and public liability insurance; its definition of dewatering includes emptying a pool (Port Stephens Council, Temporary dewatering). Its 2026/27 fee for that application is $1,020 (Port Stephens 2026/27 Fees and Charges, p.93 (PDF)). Allow time for that assessment, or plan another destination for the water.
Draining to sewer. Hunter Water says surface water and groundwater are generally a prohibited discharge to sewer (Hunter Water, Contaminated surface or groundwater discharge to sewer), and Port Stephens says requests to discharge to the sewer go to Hunter Water in writing and are typically not permitted. A tanker to an EPA-licensed facility is the usual fallback. The pool draining guide covers the options.
A new structure with its own plumbing. Demolishing a pool house with a toilet or sink, or building something new where the pool was, brings its own plumbing work and approvals. Sort these out with the certifier before work starts.
Newcastle City Council vs Lake Macquarie City Council
Both are in the “Newcastle and Hunter” area where Building Commission NSW handles plumbing inspections, so the plumbing points above apply to both. What differs is the planning paperwork. City of Newcastle’s demolition guide describes exempt, CDC and DA pathways and lists “Hunter Water stamped” plans among the CDC documents (City of Newcastle, Demolition). Lake Macquarie says demolishing buildings and structures “generally require some form of approval”, either a CDC or a DA (Lake Macquarie City Council, Demolition). If one of the council-facing s68 items applies, ask that council how to apply and how long it takes. Maitland, Cessnock and Port Stephens publish their own pages; the council approval guide links them.
Hunter Water involvement
Hunter Water assesses plans for projects “like new homes, extensions, sheds, pools, decks or retaining walls” before construction starts; the plan stamping fee is $28.20 and assessment usually takes 3 to 5 business days, and a project close to or over its pipes may need a build over asset application ($183) (Hunter Water, New home or renovation). Ask the certifier whether your removal plans need stamping.
Its connection standard allows residential pool backwash to sewer only through a trap and air-gap connection, normally an overflow relief gully, with the work done by a licensed person; direct connection to the sewer is prohibited (Hunter Water, Standard Wastewater Service Connections, section 5.9 (PDF), Version 4, March 2024). When the pool goes, the plumber should leave that connection as Hunter Water requires.
What pool removal doesn’t require under s68
Section 68’s list does not include demolishing the pool shell, excavation and backfill, removing equipment from the pad, or landscaping. Those are dealt with by the planning approval (or are exempt), and the fill has to meet the CDC or DA conditions. A full pool removal also takes out the pipework, which the underground pipes guide explains.
FAQs
If I don’t drain the pool to the sewer, do I still need s68 approval?
Not for the sewer. Hunter Water treats surface water as generally prohibited to sewer anyway, so many jobs use a tanker to an EPA-licensed facility. Discharging to a council gutter or drain needs council approval, which Port Stephens issues as a dewatering permit.
Does the s68 approval come with an inspection?
Council s68 approvals can carry inspections, but in the Hunter the plumbing cap-off is normally inspected through Building Commission NSW, with the plumber lodging a Notice of Work before and a Certificate of Compliance after. Ask the plumber for a copy of the certificate.
Do I need to lodge the s68 application before starting the job?
Any approval, s68 or planning, has to be in place before the work it covers starts. Lake Macquarie City Council says a CDC must be obtained before demolition works, and demolition needing a DA must not be carried out until that approval is obtained.
Sources
- NSW Planning Portal: Section 68 approvals (updated 02/12/2025), checked 16/11/2026
- NSW Planning: Demolition of buildings (updated 23 March 2026), checked 16/11/2026
- NSW Government: Plumbing inspection documents, checked 16/11/2026
- Port Stephens Council: Temporary dewatering, checked 16/11/2026
- Port Stephens Council: 2026/27 Fees and Charges (PDF) (dewatering application, p.93), checked 16/11/2026
- Hunter Water: Contaminated surface or groundwater discharge to sewer, checked 16/11/2026
- Hunter Water: New home or renovation (plan stamping and build over asset fees), checked 16/11/2026
- Hunter Water: Standard Wastewater Service Connections, Version 4 (PDF, March 2024) (section 5.9, pool backwash), checked 16/11/2026
- City of Newcastle: Demolition guide, checked 16/11/2026
- Lake Macquarie City Council: Demolition, checked 16/11/2026