A geotechnical report matters after a pool fill-in when something will be built over the area, when the approval or a certifier asks for one, or when a buyer’s engineer will want evidence of what is in the ground. For lawn or garden only, records of the fill and how it was compacted are usually what an owner keeps. The catch is timing: the density of compacted fill can only be tested properly while it goes in, layer by layer, so decide before backfilling starts.
Compaction Testing vs a Geotechnical Report
Compaction testing checks that each layer of fill reached a specified density. Laboratories measure density against a reference test such as AS 1289.5.1.1, the Standards Australia method for the dry density and moisture relationship of a soil using standard compactive effort (Standards Australia, AS 1289.5.1.1-2017). The engineer or certifier who specifies the fill sets the density target; this site does not publish one, because it depends on the intended use.
A geotechnical report goes further. An engineer looks at the fill and the natural ground around and beneath it to advise on footings for a particular structure. For houses, footing design draws on AS 2870-2011, Residential slabs and footings, which sets out how a site is classified (Standards Australia, AS 2870-2011).
Both often cite AS 3798-2007, the earthworks guideline engineers and certifiers reference; it is a guideline, not a law, and Standards Australia lists it as pending revision (Standards Australia, AS 3798-2007).
When Each Is Worth Having
| Plan for the area | What to arrange |
|---|---|
| Lawn or garden only | Fill and compaction records; testing optional |
| A light shed or deck | Ask the certifier or engineer what they need before backfill |
| A garage, granny flat or extension | An engineer’s specification and testing during backfill, then advice for the footing design |
| Selling later | Whatever records exist: fill dockets, test results and the approval |
Two rules frame every case. The NSW Demolition Code requires the site of a removed pool to be restored to the adjoining ground level with compacted fill (NSW Planning, Demolition of buildings), and Kiama Council’s explanation of the state rule says only certified clean fill or certified excavated natural material may go in, with no demolition waste (Kiama Council, Removal of a swimming pool). None of the five Hunter councils publishes its own fill standard for a removed pool. The VENM and ENM guide explains the fill classes.
In a mine subsidence district, demolition is on Subsidence Advisory NSW’s exempt list but backfill is not listed either way, so ask Subsidence Advisory whether your backfill, or anything built over it later, needs approval (Subsidence Advisory, Exempt developments).
Partial Fill-In: The Buried Shell
A fill-in leaves the lower shell under the fill. The shell was not designed as a footing, so if anything may be built there, have an engineer advise before choosing the method; full removal leaves nothing buried. The building over a filled-in pool guide covers the options.
Who Arranges It and What It Costs
The contractor can arrange density testing during the fill if it is in the quote; ask for it as a line item. A geotechnical engineer is engaged by the owner or builder when a structure is planned. To check a laboratory’s accreditation, NATA, which accredits organisations performing testing, publishes a search of accredited organisations (NATA).
No published source this site could verify gives a Hunter or NSW price for compaction testing or a geotechnical report after a pool fill, so get written fees from the tester or engineer. The excavation and backfill page covers the fill work itself.
Records to Keep
- The approval, and the certifier’s or council’s closing record (see final sign-off).
- Fill delivery dockets showing the material and supplier.
- Layer-by-layer test results, if testing was done.
- Any geotechnical report or engineer’s advice.
FAQs
Can I get compaction test results without a full geotechnical report?
Yes. Testing during backfill reports on the fill’s density; a geotechnical report is the engineer’s wider advice for a particular structure. The compaction certification guide covers testing in more detail.
Can the fill be tested years later?
An engineer can investigate older fill, but it is harder to prove density after the fact than to test each layer as it goes in. If building is likely, test during the fill.
Do I need a report for a partial fill-in?
If anything may be built over the area, ask an engineer first, because the buried shell was not designed to carry a footing.
To have testing priced into a removal, request a quote; the enquiry may be passed to an independent contractor who quotes in their own name.
Sources
- Standards Australia, AS 1289.5.1.1-2017: soil compaction test method, standard compactive effort; checked 15/11/2026
- Standards Australia, AS 2870-2011: residential slabs and footings; checked 15/11/2026
- Standards Australia, AS 3798-2007: earthworks guideline status; checked 15/11/2026
- NSW Planning, Demolition of buildings: compacted fill rule; checked 15/11/2026
- Kiama Council, Removal of a swimming pool fact sheet: a council’s explanation of the state rule on fill; checked 15/11/2026
- Subsidence Advisory NSW, Exempt developments: demolition exemption; checked 15/11/2026
- NATA: accreditation of testing organisations; checked 15/11/2026