When a large deck wraps around a pool, the part over and beside the pool usually has to come off first, so the excavator can reach the shell and no deck footing is left standing on coping that is about to be broken out. Part of the deck can sometimes stay, if its footings are independent of the pool and the machine can still get in. Deck demolition is a separate line in the quote: no independent source publishes a Hunter price for it, so ask each contractor to price it on its own.
This page is about taking a deck off before or during removal. For building a new deck over the filled area, see the deck over a filled-in pool guide.
Why the Deck Usually Comes Off First
- Reach. The excavator’s breaker and bucket need to work from the pool edge. Decking, joists and bearers over the coping are in the way.
- Footings on the pool. Deck posts and stumps are often set close to, or on, the pool’s concrete edge. Breaking the shell first could leave part of the deck unsupported.
- The pool fence. Glass or aluminium barrier panels are often fixed to the deck frame, and they are in the work area.
The usual order is: deck boards, joists and bearers off; footings out; pool perimeter exposed; pool demolished and backfilled; then the area finished, with or without a new deck. The full pool removal page covers the pool stage, and the concrete pool removal page covers breaking out a concrete shell.
Can Part of the Deck Stay?
Sometimes. If one end of the deck serves the house (an entertaining area off the back door) and the pool sits at the other, the pool-side section may come off while the rest stays. That depends on:
- whether the retained section has its own footings, not ones shared with the pool
- whether it can be properly supported once the adjoining section is gone
- whether the machine can still get to the pool with it in place
A builder or engineer, not the demolition crew alone, should confirm that a cut-back deck is structurally sound. If side access is already tight, the tight-access guide explains the options.
Approvals
Under NSW rules, a pool usually comes out under a complying development certificate (CDC) or a development application (DA); demolition can be exempt only where the structure could itself be built as exempt development. Include the deck, any pergola or roof over it, and the pool fence in the description of work, and ask the certifier whether they are covered by the same approval. A roofed structure attached to the house deserves a direct question, because it changes what is being demolished.
While the pool can still hold more than 30 cm of water, the NSW barrier rules still apply, so check with council before the pool fence on the deck comes down.
Old Materials and Waste
- Hardwood boards in good condition can often be reused or sold second hand; ask the contractor to set them aside if you want them.
- Composite boards and metal subframes may be accepted by the supplier or a metal recycler.
- Concrete footings go with the pool rubble. Benedict Recycling at Mayfield West lists clean segregated concrete under 700 mm at $93.12 per tonne, including GST and the waste levy; City of Newcastle’s Summerhill centre charges $451 per tonne for mixed loads including bricks, tiles and concrete in 2026/27, including GST.
- Fibro sheeting used as skirting under an old deck or on a pool shed may contain asbestos: SafeWork NSW says non-friable asbestos cement sheeting was common from the 1940s to the late 1980s. Have suspect material tested before demolition; the asbestos guide covers the steps.
What the Quote Should Show
- deck demolition as its own line: boards, frame, footings, pergola or roof
- which part of the deck stays, if any, and who confirms it is sound
- what happens to the pool fence panels
- where the timber, metal and concrete go, with dockets for the concrete
- any asbestos testing and who removes it
- the finished surface where the deck and pool were
The pool removal cost guide has published ranges for the pool itself and the local tip fees.
Pool and Deck Removal FAQs
Who demolishes the deck: the pool removal contractor or a builder?
Many pool removal contractors include a timber or composite deck in their scope. A deck with a roof attached to the house may need a builder as well; ask each contractor what they will and will not take on.
Do I need approval to remove the deck?
Include it in the pool removal application and ask the certifier. NSW rules allow exempt demolition only where the structure could itself be built as exempt development.
Can the glass pool fence be reused?
Often, if the panels and hardware come off undamaged. Any fence around a new pool or spa must meet the barrier rules in force at the time.
Can I build a new deck over the filled pool?
Usually, with fill placed and compacted for the purpose and footings designed for it; the deck over a filled-in pool guide linked above covers the detail.
Request a quote and include a photo of the deck and its footings next to the pool.
Sources
- NSW Planning: Demolition of buildings (exempt demolition, CDC), checked 15/11/2026
- NSW Government: Owning a pool or spa, your obligations (barriers; updated 16 March 2026), checked 15/11/2026
- Benedict Recycling: 2026 gate fees, Newcastle (PDF) (from 1 July 2026), checked 15/11/2026
- City of Newcastle: Summerhill fees and payment (2026/27), checked 15/11/2026
- SafeWork NSW: Asbestos, checked 15/11/2026